Buderim Dog Park - Stage 1 Update
I am pleased to provide the Buderim Dog Park project (the Project) progress update for 2023. The Project program is split into two delivery stages (Figure 1) and works have progressed as per program.
Stage 1 is 90% complete and the construction team have demobilised from site. Outstanding scope for Stage 1 is the Parks and Gardens work package, which is due for completion mid-February 2023 pending weather conditions.
The following works on Stage 1 have been completed:
installing the clay layer to design thickness to cap waste
installation of topsoil
installation of turf
installation of the pedestrian footpath
installation of sandstone seats
watering of the turf
Stage 1 works still to be completed are as follows:
replacement of fence
installation of mulch around trees along the fence line
any minor defects
The construction program identifies a Stage 1 completion date of 24 February 2023.
Completion of Stage 1 is dependent on a suitable level of turf establishment to limit damage when reopening to the public.
Stage 2 dog park area and small dog park remain accessible to the public.
Stage 2 is anticipated to commence on 27 February 2023.
The program currently identifies Stage 2 completed on 21 April 2023 and opening to the public early June pending turf establishment.