Buderim Dog Park Receives Major Overhaul

Buderim Dog Park - Stage 1 Update

I am pleased to provide the Buderim Dog Park project (the Project) progress update for 2023. The Project program is split into two delivery stages (Figure 1) and works have progressed as per program.

Stage 1 is 90% complete and the construction team have demobilised from site. Outstanding scope for Stage 1 is the Parks and Gardens work package, which is due for completion mid-February 2023 pending weather conditions.

The following works on Stage 1 have been completed:

installing the clay layer to design thickness to cap waste

installation of topsoil

installation of turf

installation of the pedestrian footpath

installation of sandstone seats

watering of the turf

Stage 1 works still to be completed are as follows:

replacement of fence

installation of mulch around trees along the fence line

any minor defects

The construction program identifies a Stage 1 completion date of 24 February 2023.

Completion of Stage 1 is dependent on a suitable level of turf establishment to limit damage when reopening to the public.

Stage 2 dog park area and small dog park remain accessible to the public.

Stage 2 is anticipated to commence on 27 February 2023.

The program currently identifies Stage 2 completed on 21 April 2023 and opening to the public early June pending turf establishment.